Parkside Studios brought its 80,000 sq ft estate onto a fully managed network in six days, using the Fortinet equipment already on site
- Excellent Reviews on
- 90 day guarantee
- Calls answered by a person in under 60 second
- Cyber Essentials
- Microsoft Partner
- ISO 27001
- ISO 80001
Company
Parkside Studios
Sector
Film and television production studios
Size
Three buildings and four workshops across more than 80,000 sq ft
Location
Wokingham, Berkshire
Services used
Network recovery and reconfiguration, three leased-line installations, Fortinet cloud management and managed network support
Headline result
The full estate network was commissioned using the existing equipment, with three leased lines installed and every stage delivered on time
An inherited network ready to be brought into service
Parkside Studios is a film and television production facility in Wokingham, around an hour from central London.
The estate includes sound stages, workshops, warehouse space and production offices across more than 80,000 square feet. Productions can occupy the site for several months at a time, bringing large teams, strict schedules and an immediate need for reliable connectivity.
When Parkside took control of the estate, enterprise-grade Fortinet equipment was already installed throughout the site. There was a firewall, five switches and around 20 wireless access points.
However, the management access and documentation had not transferred with the site.
The administrative credentials were unavailable, the cloud-management licences had expired and 17 access points had been taken down and placed into storage. There was no complete record of where they had previously been positioned.
The studios were not yet occupied by production tenants. With the first tenants due to arrive, Parkside needed the infrastructure assessed, commissioned and ready for use before they moved in.
The project also needed to provide the high-capacity internet connections that future productions would depend on. This included installing three leased lines across the estate alongside bringing the internal network into service.
Make use of the investment already on site
Replacing the equipment would have meant writing off a significant investment before establishing whether the hardware was still suitable.
We began with a survey of the complete estate.
That meant walking the three buildings and four workshops, locating every switch, access point and communications cabinet, and recording how the site was connected.
Some of the cabinets were positioned above stage height, so the survey also considered how the equipment could be reached and maintained once productions were operating on site.
The existing hardware used current Wi-Fi 6 technology and remained suitable for the estate. We recommended bringing it back into service rather than replacing it.
The plan was to factory-reset each device, remove the previous configuration and rebuild the network from a clean starting point. We would renew the Fortinet cloud-management licences, remount the stored access points, apply a documented configuration and test coverage throughout the estate.
Alongside the internal network work, we installed three leased lines to provide the permanent internet connectivity required across the studios.
Six site days, carefully sequenced
The work was delivered over six site days and coordinated around Parkside’s deadline for welcoming its first production tenants.
Temporary connections and spare wireless equipment were used at the beginning of the project to bring key areas online while the permanent network was being prepared.
Over the following days, the inherited firewall, switches and access points were factory-reset, documented and configured from a clean starting point. The routers for the three leased lines were prepared and installed, replacement access points were fitted where needed and the equipment was registered for central cloud management.
The work progressed across the stages, workshops, production offices and operational areas in a planned sequence. This allowed each part of the estate to be commissioned and tested without waiting for every permanent connection to be available.
Where cabling and termination issues were discovered during commissioning, they were corrected before the network was brought fully into service. Media converters and other supporting equipment were also installed where required to connect different parts of the estate.
The final site days moved the remaining areas from temporary connectivity onto the permanent configuration, completed the leased-line connections, remounted the remaining access points and tested wireless coverage throughout the property.
Documentation was updated throughout the project rather than reconstructed after the installation had finished.
Designed for separate production tenants
The wider network design reflected how Parkside would operate once production tenants began moving in.
Each production would need private network access without being able to see another tenant’s devices.
We designed a single network name for the estate, using private pre-shared keys to place each production into its own network segment. A key can be issued when a tenant arrives and revoked when the production wraps, without changing the wireless network for everyone else.
This gives Parkside a practical way to manage access as productions move in and out of the studios.
We also advised Parkside against applying standard office-style internet restrictions to tenants.
Film and television teams often bring their own systems, services and specialist equipment. Their route to the internet therefore needs to remain open enough for production work while the network maintains separation between different tenants.
Six site days
Three leased lines installed
Three leased lines and a managed estate-wide network
All stages were completed by the agreed dates, including the deadline connected to the first incoming tenants.
Coverage testing succeeded across the buildings using the existing access points, so Parkside did not need to purchase a replacement wireless estate.
Three leased lines were installed to provide high-capacity internet connectivity across the site. The internal network was then configured to make that connectivity available throughout the buildings, stages and workshops.
The inherited Fortinet equipment is now centrally managed, documented and supported as part of one estate-wide network.
Firmware updates can be managed proactively, configurations are backed up centrally and the network can be monitored as a whole.
If a managed device needs replacing, its saved configuration can be applied to the replacement rather than recreated from the beginning.
The project retained the enterprise-grade equipment already at Parkside, installed the permanent internet connections and prepared the estate for its first production tenants.
Six days of on-site work brought the three buildings and four workshops into service, with each stage completed by the date Parkside had planned around.